Dale Place an exclusive development of four brand-new, three-bedroomed homes designed by acclaimed local architects Sidey Design Architecture and built by Tophaven Sustainable Construction, experienced professionals with a reputation for building high-quality, energy-efficient homes.

Close to regarded primary and secondary schools and the wealth of town-centre amenities, not to mention the rolling fields of the open countryside a few streets away, the prime location of Dale Place will be an undeniable attraction for professional couples, families and retirees alike.

Plot 1 showcases a detached three-bedroomed home, whilst plots 2, 3 and 4 comprise three mews-style homes; all four plots enjoy allocated off-street parking and fully enclosed rear gardens. All four homes include on the ground floor an entrance hall, cloakroom, kitchen/dining room and lounge, whilst a landing, master bedroom with en-suite, two further bedrooms and bathroom complete the first floor.

The high specification of the properties’ interiors is evident throughout: from the sleek high-gloss kitchen units and integrated appliances; modern white sanitaryware with chrome taps and complementary wall tiling; to the uPVC double-glazed windows and doors with chrome handles. Meticulous attention has been paid to every detail gifting you more valuable time to enjoy living in your new home.

SEE OUR 'BLOG' AT THE BOTTOM OF THIS PAGE TO FIND OUT THE VERY LATEST PROGRESS.

Agents Note: Prospective buyers should note that the floors plans are not scale and are for guidance only. Also, the final layout, dimensions, finishes and landscaping of the completed property may vary.

site_plan_amended_25_may_green_17

dale_place_brochure_v8_not_ol_(2)_(1)-4

plot_2

plot_3

plot_4
cropped_price_list_july_2017

Dale Place Blog

Monday 14th August 2017:

The development is a hive of activity this morning. Plot 1 is looking very good indeed having reached 'first-fix'; internal stud-work complete, electric cabling complete, pipework for heating and plumbing complete, windows installed, front door and rear French doors installed and the plastering is well underway! Plots 2, 3 and 4 are also taking shape with the foundations and utilities in, scaffolding erected and brick work well underway.

Tuesday 15th August 2017:

Plots 2, 3 and 4 are taking shape with the foundations and utilities in, scaffolding erected and brick work well underway.

Monday 21st August 2017:

Work within Plot 1 is forging ahead; plastering almost done and some decorating underway.